Ocean Winds RV Park Vancouver Island August 2021 Update

August 2021 Update

Hello Everyone, hope you all are staying safe and healthy. We’ve been very busy on site and we will be able to start moving people in prior to October 1. We will be in contact with each of those with a reserved spot to schedule move in windows and are so looking forward to finally welcoming you…

Read more

July 2020 Update

Hi Everyone, I hope everyone is enjoying some summer weather and staying safe. We have been making decent progress on site – please see the attached pictures.  The clubhouse is taking shape and is going to be a spectacular building.  On site grading, fill and servicing is ongoing, as well as grading and leveling for…

Read more

March 2020 Update

Hi Everyone, First of all, we sure hope everyone is doing well and staying safe during these awkward and unnerving times.  I think we are all uneasy and hoping for some good news on the near horizon. Every industry is impacted by this situation and our contractors and sub contractors are doing everything to ensure…

Read more

January 2020 Update

Hi All,   Good News!  The outstanding permits have arrived and we are back on track.  We expect to have our construction crew back on site early next week – hopefully we get some good dry weather and can make up some time.  We will have a better idea of the timing for the park…

Read more

December 2019 Update

Hi Everyone,   Hopefully all is well, especially as we roll into the holiday season. It has been a frustrating few months on site as we continue to diligently pursue some outstanding permits, and unfortunately the delays in the permits have significantly affected our schedule.  In fact, at the moment, we have moved our construction…

Read more

September 2019 Update

Hello everyone, hope summer treated you well.  It seems like we have gone straight from summer weather to a wet fall.   We continue to motor forward on the site, but have definitely run into some construction frustrations.  We have been anxiously awaiting some third party approvals (BC Hydro, Agricultural Land Commission, Capital Regional District)…

Read more

July 2019 Update

    Hi Everyone, hope summer is treating you well!! We continue to make progress on the construction at Ocean Winds, although in an ideal world we would have it all done and have everyone enjoying summer in the park. The contractors have been making reasonable progress on the site, a few surprises, but nothing…

Read more

May 2019 Update

Hello again from Ocean Winds, hope everyone is enjoying the lovely spring weather!   We have attached some recent pictures from the site, the first phase is definitely taking shape.  We have the roads rough graded and in place and are working on all of the services.  Hopefully the dry weather continues!   As mentioned…

Read more

April 2019 Update

Happy Spring everyone from the team at Ocean Winds! We’ve attached some recent photo’s from the site (April 5) – lots of work to do yet, but no major surprises.  Hopefully we continue to have warm, dry weather and everything stays on schedule! We have had a very good response to our request for applications…

Read more

March Update – Now Accepting Applications for Phase 1

Hello again from Ocean Winds! We are progressing well on site despite the snow and cold weather. We have a number of machines on site now clearing all of the organic materials and topsoil and levelling & tiering the site. As they progress we will have a better sense of the timing for occupancy -…

Read more

February Update – Construction Underway

Hello again everyone, it has been some time since our last update, sure hope everyone’s winter is going well!   We continue to make progress on the site, although it is slower than we would have hoped. As you can see in the attached pictures, the site is entirely cleared and it is very interesting…

Read more

September Update – Breaking Ground

Greetings everyone, hopefully summer was enjoyable all around. Great news, we are finally officially under construction on site! The environmental clearance was issued in early September and our crew are mobilizing quickly to take advantage of hopefully a long dry autumn. Our continued hope, weather permitting, is that we have the first phase of the…

Read more